Public tool

GW Charges Calculator

PWRDA fee and charge estimators — extraction charges, application fees, groundwater compensation (GCC), and non-compliance penalties.

Reference

Table 6.1 — Compensation rates

Daily slab-wise GCC (₹/m³/day). Worked example shown below the table.

Assessment areaUp to 10> 10 up to 50> 50 up to 500> 500 up to 2,500Above 2,500
GREEN28122028
YELLOW412182836
ORANGE616243644

Table 6.1 — compensation rate in ₹/m³ per day (progressive slabs). Total GCC per day = sum of (volume in each band × rate). Multiply by chargeable days after deducting the Table 3.1 transition period.

Worked example

Orange zone, 35,000 m³/month, applied 4 months 21 days late → 3-month transition → 51 chargeable days. Monthly charge ₹5,31,600; GCC/day ₹35,512; total GCC ₹18,11,112; delay payment ₹47,844.

Table 6.1

Groundwater Compensation Charges (GCC)

Calculate GCC for delayed permission (Table 6.1) plus optional delay payment on overdue groundwater charges. Pre-filled with the PWRDA worked example (Orange, 35,000 m³/month, 4m 21d late).

Months and days until application was filed.

For delay payment (Table 6.2, item 11): monthly charge × months × 3%.

MeterNote is an independent platform. Estimates follow published PWRDA Directions 2023 tables and are for planning only — not official billing or regulatory determinations.